Search

The project is part of a broader initiative undertaken by the City of Łódź aimed at improving the management of stormwater and meltwater. The existing open tank at Liściasta Street no longer met the requirements regarding the volume of retained water or the quality of its treatment.

 

Effective stormwater treatment is essential due to runoff from the nearby residential area, which flows through the stormwater drainage system. Until now, partially treated water was discharged directly into the tank and the Sokołówka River, which runs through the area.

The installation of a new tank employing environmentally friendly technologies improves both retention efficiency and water treatment quality, benefitting the surrounding environment.

 

The total project cost amounted to PLN 5.1 million gross.

The project, titled “Nature Supported by Technology – A Retention Tank with a Hydrofit Pre-Treatment System at Liściasta Street in Łódź”, was implemented by Ecol-Unicon and received 1st Prize in the “Environmental Protection” category at the Smart City Poland Award 2024 competition.

 

 

 

Moreover, the project has been included on the map of good practices in Interreg Europe – a program co-funded by the European Union. Its aim is to facilitate the exchange of knowledge and experiences in sustainable and innovative solutions across Europe.

Scope of work

  • Design of the stormwater pre-treatment facility modernization
  • Demolition of existing pre-treatment structures
  • Construction of a retention tank with a total capacity of 900 m³
  • Construction of the hydrofit pre-treatment system
  • Installation of pre-treatment devices, including sedimentation tanks, separators, and tanks
  • Construction of process pipelines
  • Installation of control, automation, and water pre-treatment measurement systems
  • Construction of fencing, access roads, pedestrian pathways, and surface hardening for pre-treatment facility maintenance

How does the implemented solution work?

In the newly constructed facility in Łódź, we implemented the HYDROZONE BENEFIT retention tank, one of the most advanced solutions available. It enables not only water retention but also its reuse, achieved through pre-treatment devices and the operation of a hydrofit system with appropriately selected vegetation.

 

How does it work? The retention tank, with a total capacity of 900 m³, collects stormwater, which is pre-treated as it flows through a series of devices that remove suspended solids and floating contaminants. Hydrocarbon substances are eliminated using a lamella separator. Additionally, organic pollutants are filtered out in the hydrofit section, thanks to the planted vegetation and gravel layer. To keep the retained water fresh, aeration and flushing jets have been installed. These devices supply oxygen to the tank, preventing water stagnation and decomposition.

The retention tank installed by Ecol-Unicon is divided into three sections:

 

  1. Operational Section (0.5 m height, 150 m³ capacity) – The water collected here is reused for municipal purposes, such as street cleaning, channel flushing, green space irrigation, and sewer maintenance. Additionally, it supplies water to the hydrofit section during dry periods. In such cases, the water circulates in a closed loop, flowing through the filtration layer and back into the tank to ensure continuous plant irrigation.
  2. Working Section (1.5 m height, 450 m³ capacity) – This section retains incoming stormwater, which is subsequently pumped into the hydrofit system for treatment of organic pollutants.
  3. Emergency Section (1.0 m height, 300 m³ capacity) – This section provides overflow retention in case the working section reaches its capacity, for instance, during pump system failures.

Ecol-Unicon was also responsible for surface development around the pre-treatment facility. The area surrounding the tank and the Sokołówka River serves as a recreational space for the residents of Łódź, making the visual aspect of the project equally important.

 

The investment at Liściasta Street in Łódź demonstrates a comprehensive approach to stormwater retention. The project focuses not only on water storage but also on pre-treatment, enabling its reuse for municipal purposes and green space irrigation.

Such technological solutions reflect the latest global trends, which, in the face of climate change, aim not only to retain water but also to reuse it for other purposes.

 

An implementation on this scale is truly innovative and paves the way for future projects. It can be successfully applied in urban areas dominated by concrete surfaces and other sealed city squares, offering a much-needed introduction of greenery to such spaces.

 

The use of a prefabricated tank significantly shortened the installation time, allowing the project to be completed within the planned schedule. The project was carried out in a city park with limited available space, which required careful intervention in the existing tree stand. We selected construction methods that minimized tree felling to the necessary minimum. The earthworks were conducted in the Sokołówka River valley, where the groundwater level was high. Here, the use of concrete and the weight of prefabricated components proved advantageous, counteracting buoyant forces and facilitating assembly onto the foundation slab.

 

Przemysław Dębski, Service Department Director, Ecol-Unicon

The first such system in Poland

The ventilation, dust removal and deodorization system implemented for the Sorting Hall at the Solid Waste Utilization Plant in Tczew is the first such system in Poland, and probably even in Europe.

 

It all started with months of research conducted jointly with the Department of Toxicology of the Medical University of Gdańsk.

Air composition analyses were carried out in the Sorting Hall as well as on its roof, in a research model specially constructed for this purpose.

 

These studies, in addition to the precise determination of chemical compounds in the air, were designed to select the most effective active carbon mixture that would be used for the deodorization phase.

 

Signing of the Innovation Partnership agreement with town municipality of Tczew took place on April 7, 2017.

Assembly and tests

Wtedy właśnie rozpoczęła się druga faza projektu czyli montaż urządzeń. Koncepcja została przygotowana przez dr inż. Andrzeja Staniszewskiego. Zakładała montaż 3 niezależnych systemów, z których każdy składał się z systemu wentylacji, odpylania i dezodoryzacji.

Montaż zakończył się odbiorami oraz rozruchem urządzeń, który nastąpił 19 lipca. W tym samym dniu wykonano również badania tzw. zerowe wspólnie z GUMed. Cały projekt wszedł w ostatnią fazę, która skupi się na badaniach pozwalających na ostateczne dopasowanie mieszanki węgla aktywnego.

 

Ecol-Unicon, jako Generalny Wykonawca Inwestycji, do współpracy zaangażował partnerów: firmę SCROL, która realizowała montaż urządzeń oraz spółkę BIOPRO odpowiadającą  za realizację badań.

Technical description of the investment

The system consists of three independent systems and several stages of research and testing enabling individual adjustment of the system.

 

Technological solutions included in the ventilation, dust removal and deodorizing system:

  • Modernization of ventilation, carried out by the implementation of three independent systems, including a new system of channels ensuring at the same time effective collection and removal of dust and selected odorogenic substances, the total length of the channels is over 160m.
  • Dedusting devices – execution of 3 independent systems ensuring efficiency up to 60 000 m3/h.
  • Neutralization of odors and selected toxic substances – construction of three independent devices ensuring the removal of odors and toxic substances. After dedusting the polluted air from the hall, it is directed to the bed, where it is cleaned as it passes through a material that neutralizes odors and toxic substances. The flow of dust-free air is realized by blowers installed in the ventilation-dedusting-deodorization process line. The neutralizers are filled with two types of bed in a total amount of 36 m3

Applied solutions

  • renovation of the metal body (sandblasting, painting),
  • replacement of the entire facility equipment,
  • flowmeter chamber has been added,
  • connecting the facility to the monitoring system.

Applied solutions

The system includes:

 

  • 6 groups of tanks – 1720 m 3 in total, all with similar equipment
    and metering
  • valve with electric drive and radar water level measurement,
  • 2 valves (supply and emptying of tanks) with electric drives,
  • separator with a bypass and a tank for oil derivatives,
  • hydrant feed pump,
  • meter of water quality and conductivity
  • water level sensors in tanks

The scope of work included:

 

  1. Development of a local precipitation model, local reference hyetograms and computer hydrodynamic models.
  2. Development of complete project documentation and obtaining the necessary arrangements, decisions, permits for the performance of the contract.
  3. Delivery and installation of the Bumerang Smart software along with the necessary equipment for its operation, controlling water retention rainfall:
     

    • electrically controlled drives on gate valves
    • quality monitoring of retained rainwater
    • network controlled valves
    • monitoring of the filling of the cross-sections of the rainwater drainage system below the tanks
    • installation of a rain gauge and a weather forecast monitoring subsystem
  4. Execution of construction works
  5. System implementation and user training
  6. The system will control and optimize the operation of the retention reservoirs installed along the existing storm sewage collectors using the latest weather data and specially created models hydrodynamics.