Applied solutions
The system includes:
- 6 groups of tanks – 1720 m 3 in total, all with similar equipment
and metering - valve with electric drive and radar water level measurement,
- 2 valves (supply and emptying of tanks) with electric drives,
- separator with a bypass and a tank for oil derivatives,
- hydrant feed pump,
- meter of water quality and conductivity
- water level sensors in tanks
The scope of work included:
- Development of a local precipitation model, local reference hyetograms and computer hydrodynamic models.
- Development of complete project documentation and obtaining the necessary arrangements, decisions, permits for the performance of the contract.
- Delivery and installation of the Bumerang Smart software along with the necessary equipment for its operation, controlling water retention rainfall:
- electrically controlled drives on gate valves
- quality monitoring of retained rainwater
- network controlled valves
- monitoring of the filling of the cross-sections of the rainwater drainage system below the tanks
- installation of a rain gauge and a weather forecast monitoring subsystem
- Execution of construction works
- System implementation and user training
- The system will control and optimize the operation of the retention reservoirs installed along the existing storm sewage collectors using the latest weather data and specially created models hydrodynamics.