Search

Zakres prac

Our client in this case was a company located in Lithuania, dealing with the distribution of various types of cereals. The project was implemented thanks to our representative in Lithuania, UAB Prespa.

 

This is our first project, delivery and installation carried out entirely by Ecol-Unicon outside Poland.

It represents a milestone in the development of the company’s activities on foreign markets, as we have already delivered not only the product itself, but the same range of services as on domestic territory, and the assembly itself took us only two days.

 

The tank measures 10m x 6m, with a capacity of 174.5 m3. Inside, it is divided into 2 parts by a wall that acts as an overflow baffle. Thanks to the baffle, the larger parts that enter the tank are retained in the first chamber, then the water overflows into the second chamber, from which it is pumped out through pumps located on the tank lid.

Applied solutions

High-efficiency coalescence separator ESK 20

 

  • Total capacity – 20 dm3/h
  • Total weight – 3100 kg
  • Weight of the heaviest element -2300 kg
  • Oil storage volume – 480 dm3
  • Diameter of inlet/outlet DN – 200 mm
  • Diameter – 1200 mm

Applied solutions

Settling tank EOS 2000 x 1:

 

  • Active volume – 5 m3
  • Total weight – 10750 kg
  • Sediment layer thickness – 80 cm
  • Diameter of inlet/outlet DN – 1000 mm
  • Diameter – 2000 mm

High-efficiency coalescence separator ESK-BH II 6/60/1200/250:

 

  • Total capacity – 15 dm3/s
  • Total weight – 3400 kg
  • Weight of the heaviest element -3300 kg
  • Oil storage volume – 220 dm3
  • Diameter of inlet/outlet DN – 250 mm
  • Diameter – 1200 mm

High-efficiency coalescence separator ESK 15:

 

  • Total capacity – 15 dm3/s
  • Total weight – 2900 kg
  • Weight of the heaviest element -2200 kg
  • Oil storage volume – 480 dm3
  • Diameter of inlet/outlet DN – 200 mm
  • Diameter – 1200 mm

Applied solutions

Further success in Lithuania. Together with strategic partner Prespa, Ecol-Unicon was honored to supply a brand new rainwater treatment line for Boar Crossing between Lithuania and Belarus. Construction works should be ended within the next few months but three sets of settling tanks and high-efficiency separators are ready to serve with good faith and fidelity to protecting the environment.

Settling tank EOS 2000 x 3

High-efficiency coalescence separator ESK 100 x 2:

 

  • Total capacity – 100 dm3/h
  • Total weight – 8200 kg
  • Weight of the heaviest element – 6300 kg
  • Oil storage volume – 1900 dm3
  • Diameter of inlet/outlet DN – 315 mm
  • Diameter – 2000 mm

High-efficiency coalescence separator ESK 80 x 1:

 

  • Total capacity – 80 dm3/h
  • Total weight – 8200 kg
  • Weight of the heaviest element – 6300 kg
  • Oil storage volume – 1900 dm3
  • Diameter of inlet/outlet DN – 315 mm
  • Diameter – 2000 mm

Neutralizer parameters

  • Total capacity – 400 m3/h
  • Gross weight – 3400 kg
  • Tank width – 2000 mm
  • Tank height – 1910 mm

The first such system in Poland

The ventilation, dust removal and deodorization system implemented for the Sorting Hall at the Solid Waste Utilization Plant in Tczew is the first such system in Poland, and probably even in Europe.

 

It all started with months of research conducted jointly with the Department of Toxicology of the Medical University of Gdańsk.

Air composition analyses were carried out in the Sorting Hall as well as on its roof, in a research model specially constructed for this purpose.

 

These studies, in addition to the precise determination of chemical compounds in the air, were designed to select the most effective active carbon mixture that would be used for the deodorization phase.

 

Signing of the Innovation Partnership agreement with town municipality of Tczew took place on April 7, 2017.

Assembly and tests

Wtedy właśnie rozpoczęła się druga faza projektu czyli montaż urządzeń. Koncepcja została przygotowana przez dr inż. Andrzeja Staniszewskiego. Zakładała montaż 3 niezależnych systemów, z których każdy składał się z systemu wentylacji, odpylania i dezodoryzacji.

Montaż zakończył się odbiorami oraz rozruchem urządzeń, który nastąpił 19 lipca. W tym samym dniu wykonano również badania tzw. zerowe wspólnie z GUMed. Cały projekt wszedł w ostatnią fazę, która skupi się na badaniach pozwalających na ostateczne dopasowanie mieszanki węgla aktywnego.

 

Ecol-Unicon, jako Generalny Wykonawca Inwestycji, do współpracy zaangażował partnerów: firmę SCROL, która realizowała montaż urządzeń oraz spółkę BIOPRO odpowiadającą  za realizację badań.

Technical description of the investment

The system consists of three independent systems and several stages of research and testing enabling individual adjustment of the system.

 

Technological solutions included in the ventilation, dust removal and deodorizing system:

  • Modernization of ventilation, carried out by the implementation of three independent systems, including a new system of channels ensuring at the same time effective collection and removal of dust and selected odorogenic substances, the total length of the channels is over 160m.
  • Dedusting devices – execution of 3 independent systems ensuring efficiency up to 60 000 m3/h.
  • Neutralization of odors and selected toxic substances – construction of three independent devices ensuring the removal of odors and toxic substances. After dedusting the polluted air from the hall, it is directed to the bed, where it is cleaned as it passes through a material that neutralizes odors and toxic substances. The flow of dust-free air is realized by blowers installed in the ventilation-dedusting-deodorization process line. The neutralizers are filled with two types of bed in a total amount of 36 m3

Customer needs

The client struggled with the excessive emission of odour and toxic substances from the newly created sanitary sewage network, including as part of the project “Organizing the water and sewage management of the Słupia and Łupawa rivers in the Sierakowice Agglomeration” and “Construction of a sewage system with connections and sewage pumping stations in the villages of Mściszewice, Węsiory, Kistowo, Skoczkowo, Bukowa Góra and Żakowo in the Sulęczyno commune”.

Applied solutions

Over 100 pcs of EMF-600/570/CH sub-manhole filters with active carbon filling. Additionally, a sublimation layer was used to increase the effectiveness of removing odours.

Applied solutions

ESS-PE

 

Dry well pumping stations with a 2-pump system with a capacity of up to 200 m3/h. The capacity of the pumping station 14-33 l/s.

 

Retention module with dimensions:

 

  • module diameter = 2.60m
  • module height = 1.63m

The pumping station is equipped with:

 

  • Chamber – made of HDPE. There is a hole in the cover equipped with a cast iron manhole cover
  • Retention module – entirely made of HDPE. There are inspection hatches in the upper part of the module, enabling interior inspection, service, cleaning, while the pumping station is in operation.
  • Inlet and outlet piping with a diameter of 100 mm
  • 2-channel solids separators are located inside the retention module
  • Pneumatic system consisting of a compressor, air preparation station and pneumatic valves
  • Pumps (2 pieces) – mounted vertically outside the retention module. Pump protection degree IP 68. Pump operation – alternating.

Applied solutions

Dry well pumping station with a 3-pump system 
with a capacity of  Q = 310 m3/h.

Retention module with dimensions:

 

  • module diameter = 2.80m
  • module height = 3.20m

The pumping station is equipped with, among others in:

 

  • inlet-pressure piping with a diameter of 250mm
  • 2-channel solids separators are located outside the retention module (3 pieces)
  • a pneumatic system consisting of a compressor, air preparation station and 3 pneumatic valves with a diameter of DN200

The pumping station was installed in the DZB tank with the following parameters:

 

  • internal diameter: 5.50m
  • height = 7.25m

Applied solutions

Delivery, assembly and start-up of two large double pre-treatment systems:

 

Lamella separator ESL-Z 560/5600 – 4 pcs.

 

  • separator chamber dimensions 6000 mm / 4500 mm,
  • nominal capacity of the system 560 l/s,
  • maximum capacity 5,600 l/s

Two-chamber vortex settling tanks EOW-2 – 4 pcs.

 

  • diameter of the first chamber: 6000 mm,
  • diameter of the second chamber 3000 mm,
  • nominal capacity of the system 560 l/s,
  • maximum capacity 5,600 l/s,
  • capacity of the sediment section 104 m3,
  • permissible height of the sediment layer 54 cm

Delivery, assembly and start-up of two small double pre-treatment systems:

 

Lamella separator ESL-Z 100/1000 – 2 pcs.

 

  • separator chamber dimension 2500 mm
  • nominal capacity of the system 100 l/s,
  • maximum capacity 1000 l/s,
  • actual capacity of the sedimentary part 790 dm3,
  • 1950 dm3 oil storage capacity.

Two-chamber vortex sedimentation tanks EOW-2 100/1000 – 2 pcs.

 

  • diameter of the first chamber 2500 mm,
  • diameter of the second chamber 1500 mm,
  • nominal capacity of the system 100 l/s,
  • maximum capacity 1000 l/s
  • capacity of the sediment area 8.7 m3,
  • permissible height of the sediment layer 52 cm,
  • single pre-treatment system EOW + ESL-Z 40/400

Overfill, oil level and sediment alarms with GSM modem have been installed in the systems. The whole is powered by 4 triple solar systems.